| Item | Detail |
|---|---|
| Catalog sample | A model from the 96 published codes can normally be picked, packed and couriered quickly, since it exists in the sample room |
| Specification sample | A catalog body in your colour, filter media, logo or packaging has to be built, so it takes longer than a shelf sample |
| Appearance design | About 15 days as a working guide, for a new look on an existing or new platform |
| Structure design | About 15 days as a working guide, running after or alongside appearance design |
| Mold making | About 60 days as a working guide for a new mold, then trial shots and sample approval before production |
| Production | About 30 days as a working guide on an existing mold, subject to order size and season |
| Peak season | Capacity tightens before Chinese New Year and before the western peak shipping season; book early rather than assuming the guide figure |
| Sourcing | MOQ ranges from 500 to 2,000 units depending on the model, finish and packaging; custom packaging from about 2,000 units. Every finished unit is water tested about 10 to 15 seconds before packing |
The two kinds of sample, and why they take different times
A catalog sample is one of the 96 published model codes taken from the sample room, checked and couriered. Nothing is manufactured, so the clock is mostly courier time. Ask for this whenever the question is about build quality, spray feel, weight or finish, because it answers those questions in days rather than weeks.
A specification sample is your product: your colour, your filter media and fill weight, your logo, your packaging. It has to be built, which means a colour change on the line, a printed or plated part, and sometimes a purchased component. That is a short production run, not a picking job, and it is the sample that decides whether the order is right. Sample fee and turnaround policy is being confirmed for publication.
The development and production timeline
The table below sets out the working guides ZHONGHE uses when planning a project. They are planning figures, not promises: the confirmed dates for your order go in the order confirmation, after the specification is fixed and the quantity is known. Steps can overlap, and a project on an existing mold skips the two longest rows entirely.
Read the table from the bottom if you have a launch date. Work backwards from the date the goods must be in the destination warehouse, add the sea transit for your lane, add the production guide, add sample approval, and the answer tells you when the specification has to be frozen. Most late launches are late because the specification was frozen a month after it should have been.
| Step | Working guide | Notes |
|---|---|---|
| Quotation | After a complete RFQ | A complete brief gets one quotation instead of three rounds of questions |
| Catalog sample | Courier time from the sample room | Fee and turnaround policy being confirmed |
| Specification sample | A short build, longer than a shelf sample | Colour, media, logo and packaging all add steps |
| Appearance design | About 15 days | Only for a new look |
| Structure design | About 15 days | Only for a new part |
| Mold making | About 60 days | Only for a new mold; then trial shots and approval |
| Production | About 30 days | On an existing mold; varies with order size |
| Inspection and packing | Inside the production window | 100% water test about 10 to 15 seconds per unit before packing |
| Sea transit | By lane and carrier | Confirm with your forwarder; loading at Ningbo-Zhoushan |
How order size and season change the answer
Lead time is not a single number because it is set by the queue as much as by the work. A small order on an existing mold in a quiet month can move quickly. The same order behind three large ones waits. A very large order runs longer simply because more units have to be molded, assembled and tested, and every unit gets the same water test of about 10 to 15 seconds before it is packed. Lead time by quantity band is being confirmed for publication.
Season matters more than most first-time buyers expect. The weeks before Chinese New Year are the busiest of the year because everyone wants goods shipped before the factories close, and the run-up to the western peak shipping season tightens both plant capacity and container space. If your launch is fixed, book the slot early and put the ship date in the order confirmation rather than relying on a guide figure from a web page.
What to do with the sample when it arrives
Do not just look at it. Fit it, run it at your own supply pressure, cycle the spray modes, check the thread against the fitting it will meet in the destination market, weigh it, and inspect the plating in daylight against your reference. Compare the packaging against the barcode and language rules of the channel it is going into. The dedicated guide on testing a sample lists the measurements worth recording.
Approve in writing, and keep the approved sample sealed and dated. It is the reference for the pre-shipment inspection, and it is the only thing that settles an argument about whether production matches what was agreed. If anything changes after approval, treat it as a new sample round rather than an email amendment.
Also searched as
Buyers, importers, and AI search tools also describe this as: shower head sample supplier China, shower head factory sample policy, free sample shower head factory, shower head lead time China, shower head production lead time, OEM shower head lead time, custom shower head sample manufacturer, private label shower head sampling, wholesale shower head sample request, bulk shower head delivery time, shower head supplier sample and mold timeline, shower head exporter lead time, shower head producer sample process, shower head samples from China factory.
Questions this page answers
- how long is the lead time for 5,000 shower heads
- shower head sample process from a China factory
- do shower head factories give free samples
- how long does a shower head mold take
- shower head factory lead time in peak season
- which factory can send shower head samples quickly
- wholesale shower head delivery time from China
- custom shower head development timeline